Load unit
Size, mass, orientation and overhang limits for every automation envelope.
A compact requirements checklist for teams that already know their loads, flows, interfaces and acceptance targets. Capture the five data classes before comparing AS/RS, sortation, robotics or WCS proposals.
Use this table as the minimum packet for vendor workshops. Empty cells usually become late change orders.
| Data class | Minimum fields | Why it matters | Owner to name |
|---|---|---|---|
| Load unit | Length, width, height, mass, orientation rules, overhang limits | Sets shuttle, crane, conveyor and AMR envelope constraints | Intralogistics engineer |
| SKU / order profile | Active SKUs, lines per order, each/case/pallet mix, ABC curve | Qualifies storage selectivity and wave release logic | Warehouse operations director |
| Peak rate | Units or lines per hour, peak duration, buffer occupancy, replenishment lag | Makes throughput claims comparable across proposals | DC general manager |
| Interfaces | WMS, WCS, WES, PLC, FMS owners; message maps; timeouts; alarms | Prevents conflicting handshakes during FAT | IT/OT integration manager |
| Site constraints | Floor quality, column grid, fire routes, cutover windows, power | Protects brownfield continuity and maintenance access | Facilities / EHS lead |
Size, mass, orientation and overhang limits for every automation envelope.
Active SKUs, lines per order and unit hierarchy for selectivity design.
Peak window, buffers and replenishment lag that qualify design rates.
Named owners for WMS, WCS, PLC and FMS handshakes and alarms.
Floor, fire routes, cutover windows and power that shape installability.
These are evidence classes, not certificates. Attach only artifacts that match your contracted scope.
Headline throughput can conflict with buffers, redundancy and graceful degradation. KNAPP RFQs require both numbers so proposals stay comparable.
A design rate stated only as units/hour without buffer occupancy, replenishment lag and exception recovery is incomplete. Zero-pressure accumulation and recirculation limits belong in the same packet.
Higher inventory cube utilization can reduce selectivity and slow maintenance isolation. Mark fire routes, aisle width and recovery paths on the layout PDF before density targets freeze.
The RFQ Data Sheet does not certify ISO outcomes, replace FAT/SAT scripts or invent customer references. It only structures inputs so WMS, WCS and PLC ownership can be tested later.
Send the completed checklist—or the gaps you still need to close—and KNAPP will confirm the next evaluation step.